Friday, November 5, 2010

Brickwork Commenced

The Bricks started arriving on site on 18 October 2010, labourers appeared onsite on Melbourne Cup day (Tue 2 Nov) and they started sorting the piles and spreading them around the house. Then finally the brickies started putting them up on Wednesday 3 November 2010.
Unfortunately the rain has slowed them down again, but after my first site visit with the Site Supervisor this morning, I'm feeling much more confident. Weather permitting, the bricks should be completed by next Friday, and then the roof goes on!! The current plan is for early to mid Feb completion!! Keep your fingers crossed!!! :-)